WATER MAIN REPLACEMENT PROJECT
Hamilton Avenue, North, Cottage and Mill Streets
November 12-December 19, 2012
Next week, Joseph P. Cardillo & Son, Inc. will begin the water main replacement project in your neighborhood. This work includes the installation of a new water main, 5 hydrants and 51 residential service lines to the curb box at the property line.
Monday, Nov. 12
Insertion valves, tap and sleeves at the the following corners: Willow Steet and Hamilton Avenue, Hamilton Avenue and Union Street, Union Steet and Mill Street
Tuesday, Nov. 13–Wednesday, Nov. 21, 2012
Water Main Installation from Willow Street along Hamilton Avenue to North Street.
Although the roads will be open and water available during construction, please be aware that there may be disruptions. If possible, we ask that cars be removed from the street.
There will be the general foreman of the project and DPW personnel on site relative to questions you may want addressed directly. The Water Department will continue to provide updates as work progresses. You may contact John Tomasz, the Director of Public Works at 978-468-5591 or jtomasz@ hamiltonma.gov.